A 40-foot bridge built over the Banar River in Mymensingh’s Fulbaria upazila has remained completely unusable for ten years because it lacks an approach road on its western side. As a result, hundreds of local residents remain unable to cross the river using the structure.
The Department of Disaster Management constructed the bridge during the 2015-16 fiscal year at a cost of Tk 30.90 lakh. It was designed to link the Shibpur-Harirambari road in Naogaon Union to the opposite riverbank, but the project goal remains unfulfilled a decade later.
While a narrow dirt path leads up to the eastern side of the bridge, the western end opens directly into agricultural crop fields toward Harirambari village. This layout leaves travelers with no physical pathway to continue their journey onward.
Local farmer Khelu Mia stated that residents have repeatedly submitted requests to the local administration and the Union Parishad to build the missing road, but no concrete action has followed. Duly Rani Das, a resident from Palashihata village, noted that bringing the structure into operation would directly benefit hundreds of people living across nearly 10 surrounding villages.
Local representatives cited unresolved land conflicts and funding shortages as the main reasons for the delay. Union Parishad member Masud Sarkar explained that government land designated for the road has been unlawfully occupied for years, making public cooperation from Harirambari residents essential for progress.
Another Union Parishad member, Motaleb Hossain, said the responsible department initiated preliminary steps to build the road in 2024, but no funding allocation followed. He emphasized that work cannot move forward without reclaiming the land and securing necessary financial resources.
Upazila Nirbahi Officer Shahidul Islam Sohag stated that he has instructed the project implementation officer to submit a detailed report on the situation. He assured that measures to build the approach road would be initiated soon, though he did not specify a start date or budget. Meanwhile, residents continue to demand that the Tk 30.90 lakh bridge finally be made usable.